Our Recent Past Projects

List of Completed Works

 

Completed Works Last 5 Years
SL. No. Work Description Awarding Authority  Value of Work. Tk. In million Completed Financial Year Status
1 Boring, casting & Rod bainding Cast-in-situ shore pile at Chashara, Naryangonj, & Demra, Jhatrabari, Dhaka. TBEA Co. Ltd (China)
Green City Regency, B-2, (Commercial Space), Side-708, 2nd Floor, (North-East), 26 kakrail, Paltan, PS: Dhaka-1000, Bangladesh.
          550.000 2023   Successfully completed the works.
2 Road improvement Construction Works, United Teknaf land port,

United Group

(United Teaknaf land port Ltd), United House Madani Avenue, United City, Dhaka-1212

           450.000 2023 Successfully completed the works.
3 Casting & Driving of Piles (250X250 mm Dia), Length 5.5 m. & 8.5m (250X250 mm Dia) Location : Jatrabari to Demra 4 Lane Rad Project,

Toma Construction and Company Ltd.

77/1, Kakrail, Ramna, Dhaka-1000

     14.000

 

2022

 

Successfully completed the works.
4 Works for 600 mm dia Cast-in-situ pile boring casting at Chittagong Port Coloney M. Jamal and Company Limited.
House # 20/01, Road # 15 (New)
Dhanmondi Residential Area,
Dhaka-1205.

        25.000

 

2022 Successfully completed the works.
5 Works for 16″x16″ size R.C.C Pre-Cast Pile casting & Driving, Project location : Sheikh Hasina Medical College Project at Netrokona Biswas Trading & Construciton, New Market City Complex, 44/1 Rahim Square., New Market, Dhaka

  42.000

 

2022

 

Successfully completed the works.
6 Work for Cast-in-Situ pile 1000mm dia, at Construction of 280 m long pc Girder bridge over Boral River on Ershadnagar Hat- Demra up Office Road under Faridpur Upazila. L.R. Construction
House # 37, Road # 06,
Block # E, Banasree,
Rampura, Dhaka-1219.
          35.000 2022 Successfully completed the works.
7 1200mm dia pile, Casing drive, boring Casting, (with pile cap casting) at BPC Chittagong) 6 no gat ( Labour with Matrials Cost) (Jetty work) (2nd Contract)) S. S. Rahman International
TCB Bhaban (8th floor),
Karwan bazar, Dhaka-1215
          55.700 2022 Successfully completed the works.
8 Construction of 96.0 m long PSC Girder Bridge over Sotanondi Khal on Daudkandi GC Pucca road-Batakandi GC Mohanpur Launchghat Road at Ch. 0+450Km,
(Work on 1000 mm dia Cast-In-situ pile boring & casting with Rod Binding)
Md. Shajahan Khandaker & Md. Belal Mojumdar , Daudkandi, Comilla.

        32.000

 

2022

 

Successfully completed the works.
9 Works For 14″x 14″ size R.C.C Pre-Cast Pile Driving by Hydraulic Purser Rig, Project location: Akij Glass industries ltd. Anudiura, Madhabpur, Hobigonj.

Builtex Technologies Ltd.

15/4(4th floor) Mirpur Road, Shyamoli, Dhaka-1207

          25.000 2022 Successfully completed the works.
10 Work for bill 16″x 16″ size R.C.C Pre-Cast Pile Driving, Project location : Padma Railway Link Road, Saidabad – Forashgonj- Dhaka BBC Engineers Ltd.
153, Borulia, Joydebpur, Dhaka
           42.000 2022 Successfully completed the works.
11 Works for 14″x 14″ size R.C.C Pre-Cast Pile Casting. Project location : Ashrayan Project at Khurushkul, Cox’s Bazar

Biswas Trading &   Construciton. NewMarket City Complex, 44/1 Rahim Square., New Market, Dhaka

           37.50

 

2022

 

Successfully completed the works.
12 Works for 750 mm dia Cast-in-situ pile at Golora, Manikgonj Bridge Project. Rana Builders (Pvt.) Ltd.
55, West panthapath, Sheltech Tower
Dhaka-1205

         8.000

 

2022

 

Successfully completed the works.
13 Works for 1000 mm dia Cast-in-situ Pile, boring & casting, Construction of 472 M long RCC Bridge at Meghna River-Tulatuli, Camilla Hamida Traders Limited
Mahatab Centre (11th Floor), 177, Saheed Syed Nazrul Islam Sarani, Bijoy Nagar, Dhaka-1000
        52.000 2022 Successfully completed the works.
14 1200mm dia pile, Casing drive, boring Casting, (with pile cap casting) at BPC Chittagong) 2nd Contract ( Labour with Matrials Cost) ( Jetty work) S. S. Rahman International
TCB Bhaban (8th floor),
Karwan bazar, Dhaka-1215.
           75.000 2022 Successfully completed the works.
15 Works for 14″x 14″ size R.C.C Pre-Cast Pile Casting. Project location : Ashrayan Project at Khurushkul, Cox’s Bazar

N S Construction Limited       EPIC Ittefaq Point (3rd Floor), 618 Nur Ahmed Sarak (Jubilee Road), Chittagong, Bangladesh

           20.000 2021 Successfully completed the works.
16 Project Location: Labukhali, Sheak Hasina Cantonment, Work for 16″x 16″ Dia 80 feet length, 654 nos. Pre-cast Pile Driving. Confidence Construction,
House No.- 825, Monipur,
Mirpur : 02, Dhaka-1216 .
             9.000 2022 Successfully completed the works.
17 Excavation and Development of 100 feet Wide Khal along Bothe Side of Purbachal Link Road (From Kuril to Balu River) Project Construction (Package -04) (Army Project) (Sub-Contract upto Base Type-01 Advanced Development Technologies.
176, Gulshan Avenue, gulshan-2 (North), Dhaka-1212
             180.000 2022 Successfully completed the works.
18 14″x 14″ size R.C.C Pre-Cast Pile Casting and Driving. Project location : Ashrayan Project at Khurushkul, Cox’s Bazar Monico Limited Monico Bhaban, 26-27, Ring Road, Adabar Dhaka            15.000 2022 Successfully completed the works.
19 Construction of 4-Lane Khulna Coal Based Power Plant Connecting Road +2-slow moving lane +2-bus bay with Underpass Road, Under Rampal Upazila, Bagerhat District”, Package No. Bager/Rampal/01

Toma Construction and Company Ltd.

77/1, Kakrail, Ramna, Dhaka-1000

       1,170.89 2021 Successfully completed the works.
20 500 mm dia Cast-in -situ Vertical pile Borring casting Rod binding at Construction of Quay Wall, Walkway on pile, RCC Steps, Bench & Umbrella, Drainage around Quay Wall with Allied Infrastructures along the bank of Turag river form Ramchandrapur to Basila and Rayerbazar khal to kamrangirchar in Buriganga River S.S Rahman International.
TCB Bhaban (8th floor) 1, Karwan Bazar, Dhaka-1215.
           25.000 2021 Successfully completed the works.
21 Pre-cast pile driving & Casting (12″x12″), At
Project Location: Chittagong of BBL-BTC-MLB JV Project
BBL-BTC-MLB JV
New Market City Complex, 44/1 Rahim Square.
New Market, Dhaka
          15.000 2021 Successfully completed the works.
22 Constrcution of 400 & 500 dia round & square Pre -cast Pile Driving length 25 meter at Palash, Ghorashal. Ashraf Trade International.
Khanepur, Palash,
Ghorashal.
           80.000 2021 Successfully completed the works.
23 Improvement of Dharkhar to Sarail (Ch. 54+000m to 81+054m) of Cumilla (Moinamoti)-Brahmanbaria(Sarail) Highway (N-102), As 4-Lane National Highway including all structures earthwork, foundtion etc. Work for 1000 & 1200 mm dia Cast-in- situ pile borring Casting & Rod binding. Afcons Infrastructure Ltd.
Holding no.-1143, 2nd floor, Rashed Bhaban, Poritola, Poritola Bus Stand, P.O+P.S- Brahmanbaria, Post Code-3400. Bangladesh
           75.000 2021 Successfully completed the works.
24 300 feet Purbachal Bridge Project, Cast-in-situ 1200 mm dia pile Boring casting & Rod binding. Boring method Hydraulic Rotary Rig.and Load Test Biswas Builders Limited.
New Market, Dhaka
           40.000 2021 Successfully completed the works.
25 Establishment of River Port with Allied Facilities at Nagarbari, BIWTA, Jetty Piling works, 700 mm dia Cast-in-situ Pile, Boring method Hydraulic Rotary Rig. S.S Rahman International.
TCB Bhaban (8th floor) 1, Karwan Bazar, Dhaka-1215.

     140.000

2021 Successfully completed the works.
26 1200 mm Dia cast in situ pile & Load Test, Project: Dohazari – Cox’sBazar Railway Project, Lot-01 Toma Construction and Company Ltd. 77/1, Kakrail, Ramna, Dhaka-1000              32.500 2021 Successfully completed the works.
27 Boring & Casting, Situ pile 1000mm/750mm dia, pile at Nayerhat bridge, Nilphamary 4 Nos Bridge, Netrokona & Kurigram Bridge under RHD Rana Builders Ltd.
55, West panthapath, Sheltech Tower
Dhaka-1205
           52.500 2021 Successfully completed the works.
28 600mm dia & 900mm Cast-in-Situ pile Boring & Casting.
Project Location: Wasa Bhaban, Chittagong..
M. Jamal and Company Limited.
House # 20/01, Road # 15 (New)
Dhanmondi Residential Area,
Dhaka-1205.
           35.000 2022 Successfully completed the works.
29 Pre-cast pile driving (16”x16”), pile length 60 feet at
Project: United intl. Madical college at united city, satarkul, badda, dhaka-1212
United International Madical College
Gulshan Centre Point
Plot # 23-26, Road # 90-91,
Gulshan -2, Dhaka-1212
          25.000

2022

Successfully completed the works.
30 Pre-cast pile driving & Casting (16”x16”), pile length 40 feet, 5000 nos. with Bridge work At
Project: splash works water park ltd. Baushia, gazaria, Munshiganj.
Splash Works Water Park Ltd.
Baushia, Gazaria, Munshiganj
Bangladesh.
           45.00 2022 Successfully completed the works.
31 Driving & Casting of 600 mm dia Cast-in-situ Pile with permanent steel pile casing for the work – Construction of Steel Silo (Jetty Portion) at Ashugonj, Brahmanbaria.

Toma Construction and Company Ltd.

77/1, Kakrail, Ramna, Dhaka-1000    

           27.210 2022 Successfully completed the works.
32 Pre-cast pile driving (14”x14”), pile length 60 feet at
Project: Bangobundhu Madical college at Sunamgonj.
Sylhet Osmani Madcal College, Situ pile,
Nazrul Accdamey, Situ Pile
M. Jamal and Company Limited.
House # 20/01, Road # 15 (New)
Dhanmondi Residential Area,
Dhaka-1205.
          25.000 2022 Successfully completed the works.
33 1200mm dia pile, Casing drive,  boring Casting, (with pile cap casting) at BPC  Chittagong) 6 no gat  ( Labour with Matrials Cost) ( Jetty work) S.S Rahman International.
TCB Bhaban (8th floor) 1, Karwan Bazar, Dhaka-1215.
          55.700 2022 Successfully completed the works.
34 Works for Pile the purpose of Cast in Situ Piles 500 mm dia, 700mm dia to Construction of Establishment of River Port with Allied Facilities at Nagarbair-Bank Protection (Package-2), Jetty pile BIWTA S.S Rahman International.
TCB Bhaban (8th floor) 1, Karwan Bazar, Dhaka-1215.
          18.000 2022 Successfully completed the works.
35 300 feet Purbachal Bridge Project, Cast-in-situ 1200 mm dia pile Boring casting & Rod binding. Boring method Hydraulic Rotary Rig.and Load Test Biswas Builders Limited.
New Market, Dhaka
                 40.000 2022 Successfully completed the works.
36 280 m long pc Girder bridge over Boral River on Ershadnagar Hat- Demra up Office Road underFaridpur Upazil.
Boring & Casting 1000mm dia cast-in-situ piles and Rod binding including cutting, bending, G.I wire, Welding Etc. Including Bentonite
(Working Method: Hydraulic Rotary Rig )

L.R Construction
House # 37, Road # 06. Block # E, Banasree,
Rampura, Dhaka-1219

           55.000 2022 Successfully completed the works.
    Total Value of works =